A summary of our current and planned wastewater projects

sewage plant 2

Pandora industrial main

We’re upgrading the industrial main pipe from Pandora to the wastewater treatment plant to improve the serviceability of this pipe. A design and options report is underway to determine the best solution to the struvite buildup in this pipeline. 

Planned Start Date: Already underway
Construction Date: June 2020
Project Budget: $1.25M

 

Taradale wastewater diversion

Wastewater will be diverted to Taradale pump station to reduce wastewater overflows during storm events. We are currently developing a wastewater model to enable this project to be analysed before design and construction begins.

Planned Start Date: Already underway
Construction Date: Dec 2020
Project Budget: $1.1M

Loading...

Napier City Council - Copyright © 2019 Napier City Council

Disclaimers and Copyright
While every endeavour has been taken by the Napier City Council to ensure that the information on this website is accurate and up to date, Napier City Council shall not be liable for any loss suffered through the use, directly or indirectly, of information on this website. Information contained has been assembled in good faith. Some of the information available in this site is from the New Zealand Public domain and supplied by relevant government agencies. Napier City Council cannot accept any liability for its accuracy or content. Portions of the information and material on this site, including data, pages, documents, online graphics and images are protected by copyright, unless specifically notified to the contrary. Externally sourced information or material is copyright to the respective provider.

© Napier City Council - www.napier.govt.nz / +64 6 835 7579 / info@napier.govt.nz