Fees & Charges Options
Subdivision and Land Development Fees & ChargesSubdivision and Land Development Fees and Charges approved for 1 July 2012 to 30 June 2013.
All fees and charges are inclusive of GST (except as noted *).
| Processing of Resource Consents (Subdivision) | Fee (incl GST) |
|---|---|
|
Note: These set fees relate to the minimum charge only. Actual fee payable includes the cost of time taken to process each application, memorandum, consent, notice, certificate or schedule, the cost of disbursements, plus any inspections required. |
|
| Planning - Scheme Plan Approval (0-10 lots) | |
| Regulatory Engineering | $248.00 |
| Planning Component | $372.00 |
| Administration Fee | $69.50 |
| File Cost | $48.00 |
| Microfiche / Scanning Cost | $37.50 |
| Total | $775.00 |
| Planning | |
| Scheme Plan Approval (11-20 lots) | $1,674.00 |
| Scheme Plan Approval (greater than 20 lots) | $1,984.00 |
| Amendments to Flats/Crosslease | $248.00 |
| Certification Fee (223 & 348) | $124.00 |
| Certificate of Compliance (224) Regulatory Engineering | $372.00 |
| Rights of Way Approval | $248.00 |
| Document Sealing/Signing Fee | $93.00 |
| Site Visit Fee | $93.00 |
| Monitoring Inspection in relation to any consent, designation, or site inspection | $248.00 |
| Hourly Rates | |
| Regulatory Engineering | $124.00 |
| Planning Staff | $124.00 |
| Administration Staff | $69.50 |
| Conveyancing Costs | Fee (incl GST) |
|---|---|
|
Note: The following costs are for attendances by the City Solicitors on behalf of Council for the preparation and arrangement of legal documentation. |
|
| Costs | |
| Bond (includes Caveat) * | $565.00 |
| Release of Bond (includes Caveat) | $445.00 |
| Release of Bond and issue of replacement Bond (includes withdrawal of existing Caveat and creation of new Caveat) | $771.00 |
| Easement (per document) | $445.00 |
| Covenant (per document) | $445.00 |
| Certificate under Building Act | $357.00 |
| Release of Certificate, Caveat | $238.00 |
| Consent | $208.00 |
| Release of Consent Notice, Fencing Covenant | $297.00 |
| Lease Renewal | $511.00 |
| Freeholding | $511.00 |
| Engineering Approval (Assets) | Fee (incl GST) |
|---|---|
| Proposed works in terms of the code of practice | |
|
Note: The charges apply where the proposed works are in terms of D and E of the code. Note: Where the proposed works are not in terms of D and E of the code but subject to specific design then the actual cost is charged. |
|
| Minimum charge (for up to 3 lots) | $170.00 |
| Per lot for each additional over 3 | $26.00 |
| Minimum charge (staff time hourly rate) (Where there is insufficient information or amendments are required, additional charges may be made) | $120.00 |
| Bond for Completion of - As Built - Plans | |
|
Note: Bond for - As Built - plans are required for stand-alone projects (not part of a subdivision) that include infrastructure that is to be taken over by Council. |
|
| Bond calculated at 5% of estimated cost of project with a minimum of $5,000 * | $5,000.00 |
| Construction - Acceptance of Pipe Assets | Fee (incl GST) |
|---|---|
| Sewerage | |
|
Note: Initial inspection, water-tightness test, CCTV inspection and final inspection. |
|
| Minimum charge | $180.00 |
| Per lot for each additional over 3 | $45.00 |
| Stormwater | |
|
Note: Initial inspection, water-tightness test, CCTV inspection and final inspection. |
|
| Minimum charge | $180.00 |
| Per lot for each additional over 3 | $45.00 |
| Water Supply | |
|
Note: Initial inspection, pressure test, disinfection, residual check and flushing and final inspection |
|
| Minimum charge | $345.00 |
| Per lot for each additional over 3 | $57.00 |
| Charging by Metre Length | |
|
Note: Where charging by number of lots is inappropriate the following charges per metre apply
|
|
| Sewerage - Minimum charge | $180.00 |
| Sewerage - Per meter | $2.10 |
| Stormwater - Minimum charge | $180.00 |
| Stormwater - Per meter | $2.10 |
| Water Supply - Minimum charge | $345.00 |
| Water Supply - Per meter | $2.10 |
| Roading and Reserves | |
| Roading - Fixed Charge (initial inspections for construction of new roads) | $475.00 |
| Roading - plus a Per Lot charge of | $23.00 |
| Reserves - Minimum Charge (initial inspections for development of new reserves) | $540.00 |
| Reserves - Additional Inspection Charge | $100.00 |
| Financial Contributions | Fee (incl GST) |
|---|---|
|
Note: In the District Plan (refer to Rule 65.14) the formula for the increase in Financial Contributions is based on the movement in the Statistics NZ Producers Price Index (PPI) Inputs Table E Index. |
|
| Infill | |
| Urban (per lot) | $22,628.00 |
| Ahuriri (per lot) | $22,628.00 |
| Multi-Story (per dwelling unit) | $18,236.00 |
| Multi-Story (plus per hectare - Stormwater) | $52,704.00 |
| King St / Guppy Rd (per dwelling unit) | $19,012.00 |
| King St / Guppy Rd (plus per hectare - Stormwater) | $176,535.00 |
| King St / Guppy Rd (plus per metre Guppy Road frontage - if applicable) | $658.00 |
| Greenfields | |
| Lagoon Farm (per lot) | $20,381.00 |
| Mission Heights (per lot) | $19,741.00 |
| Park Island (per lot) | $20,590.00 |
| Rural | |
| Poraiti (per lot) | $15,395.00 |
| Lifestyle Character (per lot) | $16,691.00 |
| Plus for lots not connected to a stormwater system discharging above the flood detention dam | $2,317.00 |
| All other rural areas including subdistrict rural (per lot) | $13,810.00 |
| Capital Contributions | |
| Bay View Water Supply (per domestic connection) | $2,582.00 |
| Bay View Water Supply (Commercial) | Fee (incl GST) |
|---|---|
| The Greater of: | |
| (1) 15mm connection, or | $2,582.00 |
| (2) the sum of: | |
| (2a) Non residential based: | |
| (i) Offices and Shops | |
| - Gross Floor area ($ per m²) | $10.31 |
| - plus Pervious Land area ($ per m²) | $3.86 |
| (ii) Warehouses | |
| - Gross Floor area ($ per m²) | $5.15 |
| - plus Pervious Land area ($ per m²) | $3.86 |
| (iii) Unsealed yards ($ per m²) | $3.86 |
| (2b) Residential based | |
| (i) Residential Care, Travellers Accommodation and Retirement Complexes | |
| - Population per Head | $386.62 |
| - plus Pervious Land area ($ per m²) | $3.86 |
| (ii) Day Care Centres and Educational Facilities | |
| - Population per Head | $193.31 |
| - plus Pervious Land area ($ per m²) | $3.86 |
| Bay View Wastewater (Commercial) | Fee (incl GST) |
|---|---|
| The Greater of: | |
| (1) Bay View wastewater connection charge, or | See sewer connection charges |
| (2) the sum of: | |
| (2a) Non residential based: | |
| (i) Offices and Shops | |
| - Gross Floor area ($ per m²) | $7.21 |
| (ii) Warehouses | |
| - Gross Floor area ($ per m²) | $3.60 |
| (2b) Residential based | |
| (i) Residential Care, Travellers Accommodation and Retirement Complexes | |
| - Population per Head | $270.00 |
| (ii) Day Care Centres and Educational Facilities | |
| - Population per Head | $135.00 |
| Development Contributions | Fee (incl GST) |
|---|---|
|
Note: This schedule of charges for Development Contributions will become operative when Council adopts its initial LTCCP, and is indexed on 1st July in line with Council's LTCCP policies. |
|
| Roads and Transportation | |
| Roads and Transportation | $11,310.00 |
| Water Supply Contribution (Non-Residential Based) | |
| Offices and Shops | |
| - Either gross floor area ($ per m²) | $6.78 |
| - Plus pervious land area ($ per m²) | $2.54 |
| - or equivalent water connection, whichever is greater | See Equivalent Connections |
| Medical Clinics/Hospitals | |
| - Either gross floor area ($ per m²) | $8.48 |
| - Plus pervious land area ($ per m²) | $2.54 |
| - or equivalent water connection, whichever is greater | See Equivalent Connections |
| Warehouses / Factories / Network Utility Operations | |
| - Either gross floor area ($ per m²) | $3.40 |
| - Plus pervious land area ($ per m²) | $2.54 |
| - or equivalent water connection, whichever is greater | See Equivalent Connections |
| Unsealed Yards | |
| - Pervious land area ($ per m²) | $2.54 |
| - or equivalent water connection, whichever is greater | See Equivalent Connections |
| Churches | |
| - Per church | $3,395.30 |
| - Plus pervious land area ($ per m²) | $2.54 |
| - or equivalent water connection, whichever is greater | See Equivalent Connections |
| Wastewater Contribution (Non-Residential Based) | |
| Offices and Shops | |
| - Gross floor area ($ per m²) | $4.73 |
| - or equivalent wastewater connection, whichever is greater | See Equivalent Connections |
| Medical Clinics/Hospitals | |
| - Gross floor area ($ per m²) | $5.91 |
| - or equivalent wastewater connection, whichever is greater | See Equivalent Connections |
| Warehouses / Factories / Network Utility Operations | |
| - Gross floor area ($ per m²) | $2.37 |
| - or equivalent wastewater connection, whichever is greater | See Equivalent Connections |
| Churches | |
| - Per church | $2,368.20 |
| - or equivalent wastewater connection, whichever is greater | See Equivalent Connections |
| Stormwater Contribution (Non-Residential Based) | |
| Offices and Shops - Land area ($ per m²) | $4.64 |
| Medical Clinics/Hospitals - Land area ($ per m²) | $4.64 |
| Warehouses / Factories / Network Utility Operations - Land area ($ per m²) | $4.64 |
| Unsealed Yards - Land area ($ per m²) | $1.18 |
| Churches - Land area ($ per m²) | $4.64 |
| Water Supply Contribution (Residential Based) | |
| Residential Care Facilities | |
| - Population per head $ | $254.73 |
| - Plus pervious land area ($ per m²) | $2.54 |
| - or equivalent water connection, whichever is greater | See Equivalent Connections |
| Travellers Accommodation | |
| - Population per head $ | $254.73 |
| - Plus pervious land area ($ per m²) | $2.54 |
| - or equivalent water connection, whichever is greater | See Equivalent Connections |
| Day Care Centres | |
| - Population per head $ | $128.18 |
| - Plus pervious land area ($ per m²) | $2.54 |
| - or equivalent water connection, whichever is greater | See Equivalent Connections |
| Educational Facilities | |
| - Population per head $ | $128.18 |
| - Plus pervious land area ($ per m²) | $2.54 |
| - or equivalent water connection, whichever is greater | See Equivalent Connections |
| Retirement Complexes | |
| - Population per head $ | $253.09 |
| - Plus pervious land area ($ per m²) | $2.54 |
| - or equivalent water connection, whichever is greater | See Equivalent Connections |
| Wastewater Contribution (Residential Based) | |
| Residential Care Facilities | |
| - Population per head $ | $177.48 |
| - or equivalent wastewater connection, whichever is greater | See Equivalent Connections |
| Travellers Accommodation | |
| - Population per head $ | $177.48 |
| - or equivalent wastewater connection, whichever is greater | See Equivalent Connections |
| Day Care Centres | |
| - Population per head $ | $88.75 |
| - or equivalent wastewater connection, whichever is greater | See Equivalent Connections |
| Educational Facilities | |
| - Population per head $ | $88.75 |
| - or equivalent wastewater connection, whichever is greater | See Equivalent Connections |
| Retirement Complexes | |
| - Population per head $ | $177.48 |
| - or equivalent wastewater connection, whichever is greater | See Equivalent Connections |
| Stormwater Contribution (Residential Based) | |
| Residential Care Facilities - Land area ($ per m²) | $4.64 |
| Travellers Accommodation - Land area ($ per m²) | $4.64 |
| Day Care Centres - Land area ($ per m²) | $4.64 |
| Educational Facilities - Land area ($ per m²) | $4.64 |
| Retirement Complexes - Land area ($ per m²) | $4.64 |
| Equivalent Connections | |
| 15mm Diameter - Water Connection | $1,698.00 |
| 15mm Diameter - Wastewater Connection | $1,184.00 |
| 20mm Diameter - Water Connection | $3,021.00 |
| 20mm Diameter - Wastewater Connection | $2,116.00 |
| 25mm Diameter - Water Connection | $4,719.00 |
| 25mm Diameter - Wastewater Connection | $3,305.00 |
| 32mm Diameter - Water Connection | $7,732.00 |
| 32mm Diameter - Wastewater Connection | $5,415.00 |
| 40mm Diameter - Water Connection | $12,071.00 |
| 40mm Diameter - Wastewater Connection | $8,450.00 |
| 50mm Diameter - Water Connection | $18,862.00 |
| 50mm Diameter - Wastewater Connection | $13,203.00 |
| 80mm Diameter - Water Connection | $48,279.00 |
| 80mm Diameter - Wastewater Connection | $33,795.00 |
| 100mm Diameter - Water Connection | $75,440.00 |
| 100mm Diameter - Wastewater Connection | $52,808.00 |